Is Shore Power a New Fire Risk at the Berth?

By Vignesh Durai · · 6 min read

Shore power's added risk is small and sits at the 11 kV plug: arcing and electrical fire. The bigger change is a blackout if the shore supply trips.

A small one, and mostly not on the car deck. Shore power runs an 11 kV cable and plug from the quay into the ship, and EMSA's 2022 guidance lists electrical fire, arcing and blackout as its three hazards. The bigger change is operational. With the generators stopped, a trip ashore can black the ship out while it is loading.

This matters now because EU law makes shore power the default at berth for ferries from 2030, and car carriers have started plugging in without being required to. The berth is already where many ro-ro fires start: EMSA's FIRESAFE II statistics put one in four in port or just after departure. Shore power does not create that risk, but it changes the electrical plant aboard during those hours, and owners, terminals and underwriters should know how.

11 kV
Ro-pax shore connection voltage under IEC/IEEE 80005-1 Annex B; 6.6 kV accepted for regional services
6.5 MVA
Ro-pax power rating, over a single cable, as tabulated by EMSA
2030
FuelEU Maritime: passenger and container ships over 5,000 GT must use shore power at qualifying EU berths
45 s
SOLAS limit for emergency power to come on after the main source fails

Why is shore power reaching car decks now?

Because EU regulation requires it for ferries and charterers want it for car carriers. Under FuelEU Maritime, Regulation (EU) 2023/1805, Article 6, passenger ships and container ships over 5,000 GT moored at qualifying EU berths must draw their electricity from shore from 1 January 2030, with exemptions for short stays, emergencies and incompatible equipment. The berths come from AFIR, Regulation (EU) 2023/1804, Article 9: TEN-T ports averaging more than 40 calls a year by large ro-pax ships must offer shore power for at least 90% of those calls by the end of 2029.

Pure car and truck carriers fall outside the FuelEU mandate, but some are plugging in anyway. In early 2026 the 200 m PCTC Lake Shirasagi connected at Bremerhaven, which Cavotec, the shore-power supplier, describes as the first connection of a PCTC in Europe. In June 2026 ICO, an NYK Group terminal, opened Belgium's first commercial ro-ro shore-power berth at Zeebrugge. It serves one ship at a time and supplies its own cabling, so ships without onboard shore-power equipment can still connect.

What does a ro-ro shore connection look like?

One high-voltage cable, a plug and a set of safety interlocks. For ro-pax ships, IEC/IEEE 80005-1 Annex B, as tabulated in EMSA's guidance, specifies 11 kV (6.6 kV accepted for regional services) and 6.5 MVA through one cable. The cable management system sits on the berth. Pilot contacts in the cable carry the emergency shutdown, and the shore transformer's star point is earthed through a 335-ohm resistor (200 ohms at 6.6 kV). Connecting takes about 30 minutes by EMSA's estimate, or 10 minutes when automated, against an average car-carrier call of one to two days.

Where can a shore connection start a fire?

Mostly at the plug and in the shore-side converter station, not on the vehicle deck. EMSA's failure tables list contactors that fail to open, failed cooling fans and overheated switchgear, each ending in overheating, arcing or fire. Most of that equipment sits ashore. On the cable itself, the concern is contact resistance. A worn or poorly mated plug can arc, and because the cable is handled at every call, EMSA notes that the earthing risk 'is not minor'.

The standard protections are electrical, not fire detection. An earthing-check pilot wire trips the breakers on both sides if the earth conductor fails, and negative-sequence overcurrent protection (ANSI 46) on the shore relay looks for the imbalance a bad contact causes. Our technical article on loose terminals explains why ordinary overcurrent protection cannot see a high-resistance joint. EMSA also flags protection coordination. A static frequency converter supplies far less fault current than the ship's own generators, so breakers set for generator power 'may not work properly' on shore power. IEC/IEEE 80005-1 therefore requires enough fault current from shore to trip the ship's largest load.

We found no published casualty report that blames a ro-ro or ferry fire on a high-voltage shore connection. So far the risk exists on paper, in failure tables, rather than in the casualty record.

What happens to the fire pumps if shore supply trips?

The ship blacks out until its own power comes back, and that recovery depends on the ship. On a full shore-power connection the generators are stopped. If the shore breaker trips, whether from a ship fault, a converter failure or a cable crushed by quay traffic (all listed by EMSA), the main switchboard goes dead. SOLAS II-1/42 and 43 give the emergency source 45 seconds to come on, and EMSA confirms 80005-1 allows ship power to be restored on those terms after a blackout. But on most ships the emergency switchboard feeds the emergency fire pump, not every main fire pump or drencher pump.

That is why EMSA lists 'onboard readiness of incident response systems, such as firefighting equipment' as a factor in whether shore power is feasible at all. Its emergency-response list for ports names three scenarios: sustained blackout, electrical fire, and shock or arc. It adds that port emergency services should know the high-voltage installation is there. That point matters at a ro-ro berth. The NTSB's 2025 safety alert after the fatal Grande Costa d'Avorio fire at Port Newark found land-based firefighters often unfamiliar with ships, and a live 11 kV cable is one more thing they need briefing on.

Does shore power change the EV risk on the car deck?

No. The vehicles, their batteries and the way a thermal runaway develops are the same with or without shore power. What does not change either is the gap that already exists at berth: FIRESAFE II found that nearly all ships mute smoke detection on vehicle decks during loading, and the berth is when the deck holds the most recently driven, hottest cars. Shore power quiets the engine room. It does nothing for the decks above it.

The more useful question for an owner is whether the plug-in changes how the crew responds. With the generators cold, bringing the main plant back takes longer than the 45 seconds SOLAS allows the emergency source, and until it returns the main fire and drencher pumps depend on how the ship is wired. An EV fire that starts during cargo work therefore meets a ship with less electrical margin than at sea, unless the operator has planned for it.

What should an operator check before plugging in?

Treat the first connection as a fire-safety change, not only an emissions one:

  • Map which fire pumps, drencher pumps and detection panels stay powered if the shore breaker trips, and how long the main plant takes to restart.
  • Decide whether one generator stays warm, or the plant stays in parallel, during cargo operations on EV-heavy calls.
  • Agree the emergency shutdown chain with the terminal: who can open the shore breaker, from where, and how the bridge is told.
  • Brief the port fire service on the cable route and isolation point, as EMSA's guidance asks.
  • Follow MSC.1/Circ.1675, the IMO interim guidelines on safe shore-power operation, and IACS Recommendation 182 on construction and testing.
  • Inspect plugs and cable sheaths at every connection; EMSA lists wear, UV ageing and quay traffic among the failure causes.
Conclusion

How RoRoSAFE helps

Shore power changes the electrics at berth, but the fire most likely to threaten a car deck there is still a vehicle, during loading, while smoke detection is muted. RoRoSAFE watches each parked vehicle with infrared thermal and battery-vent gas sensing, and sends tiered bridge and shore alerts naming the deck and bay before visible smoke. It installs alongside the berth with no drydock, complements SOLAS systems, and holds no class type approval yet.

Pilot: one deck · installed alongside the berth · no drydock · 6 months of dashboard access

Sources

Frequently asked

Questions, answered

Does shore power increase the fire risk on a ro-ro ship?+

Slightly, and mainly outside the vehicle deck. EMSA's 2022 guidance lists electrical fire, arcing and blackout as the hazards of a shore connection, centred on the high-voltage plug, cable and shore-side converter equipment. We found no published casualty report blaming a ro-ro fire on one. The larger effect is that a shore-supply trip can black out a ship whose generators are stopped.

What voltage do ro-pax ferries use for shore power?+

IEC/IEEE 80005-1 Annex B, as summarised by EMSA, specifies 11 kV for ro-pax ships, with 6.6 kV accepted for regional services, at 6.5 MVA through a single cable. The cable management system sits on the berth, and the emergency shutdown runs through pilot contacts in the cable. Connection takes about 30 minutes manually, or around 10 when automated.

Do car carriers have to use shore power in the EU?+

Not under FuelEU Maritime, whose 2030 shore-power obligation covers passenger and container ships over 5,000 GT. Car carriers are connecting voluntarily: the PCTC Lake Shirasagi plugged in at Bremerhaven in early 2026, and ICO opened a commercial ro-ro shore-power berth at Zeebrugge in June 2026.

What happens to a ship's fire pumps if shore power fails?+

With the generators stopped, a trip ashore blacks out the main switchboard. SOLAS gives the emergency source 45 seconds to come on, but it feeds the emergency fire pump, not necessarily every main fire or drencher pump. Operators should map which systems stay live and how fast the main plant restarts before relying on shore power during cargo operations.